[Fabrication, galvanizing, testing, supply and delivery of different 132 KV Substation structures including G.I nuts, bolts and washers matching with the second main bus at Behala 132 KV Sub-station under Behala Area Office, WBSETCL under A.C.E, KTZ] open

WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED

Ref: ACE/KTZ/CIVIL/SS-Str /2025-26/15, Dated 13.03.2026 · ID: 2026_SETCL_1022251_1

Category Project Work

AI summary

This tender provides details about the project including scope of work, estimated value, deadlines, and eligibility requirements.

Overview

The tender titled "Fabrication, galvanizing, testing, supply and delivery of different 132 KV Substation structures including G.I nuts, bolts and washers matching with the second main bus at Behala 132 KV Sub-station under Behala Area Office, WBSETCL under A.C.E, KTZ" is issued by the West Bengal State Electricity Transmission Company Limited (WBSETCL). This is an open tender aimed at procuring essential structures for a substation project.

Scope / Work

The scope of work includes the fabrication, galvanizing, testing, supply, and delivery of various 132 KV substation structures, along with G.I nuts, bolts, and washers. The work is to be executed at the Behala 132 KV Sub-station, and bidders should refer to the tender documents for detailed pre-qualification requirements. The project is categorized under 'Project Work' and is expected to be completed within 120 days from the award of the contract.

Fees & EMD

There is no tender fee associated with this tender. However, an Earnest Money Deposit (EMD) of ₹55,000 is required, and no exemptions are allowed for this fee. Bidders must ensure that the EMD is submitted as part of their bid to qualify for consideration.

Key dates

  • Publish Date: 13-Mar-2026 05:30 PM
  • Document Download Start Date: 13-Mar-2026 06:00 PM
  • Document Download End Date: 24-Apr-2026 03:00 PM
  • Clarification Start Date: 13-Mar-2026 06:00 PM
  • Clarification End Date: 19-Mar-2026 03:00 PM
  • Bid Submission Start Date: 25-Mar-2026 09:00 AM
  • Bid Submission End Date: 24-Apr-2026 03:00 PM
  • Bid Opening Date: 28-Apr-2026 03:00 PM

Bidders are advised to attend the pre-bid meeting scheduled for 24-Mar-2026 at the specified location to clarify any doubts regarding the tender requirements.

AI insights

Risk factors

  • EMD size of ₹55,000
  • bid validity of 90 days
  • tight timelines for bid submission
  • no exemptions for EMD

Financials

Tender value Undisclosed
EMD amount ₹55,000 — payable to Nil at Nil
Tender fee ₹0.00 — payable to Nil at Nil

Payment mode Online

Timeline

Publish date 13-Mar-2026 05:30 PM
Bid end 24-Apr-2026 03:00 PM
Opening date 28-Apr-2026 03:00 PM

Documents available from 13-Mar-2026 06:00 PM to 24-Apr-2026 03:00 PM. Clarification window: 13-Mar-2026 06:00 PM to 19-Mar-2026 03:00 PM.

Tender Documents

How tender documents work

Sign in and verify your email to use our viewer. You can open up to 5 different documents per UTC day (each file counts once). Archives (ZIP, RAR, etc.) are download only—no in-browser preview. Need a higher limit?

Name Size Type Action
BOQ_2512709.xls 336 KB XLS
View document Sign-in required
Timeextension.pdf 107.73 KB PDF
View document Sign-in required

Corrigenda

Official amendments and notices. PDFs open in the same viewer as tender documents (sign in, verified email, daily limit applies).

1st Tiem Extension

Type Date

Published Corrigendum Details Date : 14-Apr-2026 04:36 PM [Tender information] Organisation Chain : WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED||TRANSMISSION OANDM HQ Tender ID : 2026_SETCL_1022251_1 Tender Ref No : ACE/KTZ/CIVIL/SS-Str /2025-26/15, Dated 13.03.2026 Tender Title : Fabrication, galvanizing, testing, supply and delivery of different 132 KV Substation structures including G.I nuts, bolts and washers matching with the second main bus at Behala 132 KV Sub-station under Behala Area Office, WBSETCL under A.C.E, KTZ Corrigendum Type : Date [Corrigendum:1] Corrigendum title: 1st Tiem Extension Description: 1St Time Extension Published: 13-Apr-2026 01:46 PM Document: Timeextension.pdf Size (KB): 107.73 Publish Date: 13-Mar-2026 05:30 PM │ Bid Opening Date: 28-Apr-2026 03:00 PM Document Download/Sale Start Date: 13-Mar-2026 06:00 PM │ Document Download/Sale End Date: 24-Apr-2026 03:00 PM Clarification Start Date: 13-Mar-2026 06:00 PM │ Clarification End Date: 19-Mar-2026 03:00 PM Bid Submission Start Date: 25-Mar-2026 09:00 AM │ Bid Submission End Date: 24-Apr-2026 03:00 PM Pre Bid Meeting Date: 24-Mar-2026 03:00 PM [Critical Dates] [Details Before Corrigendum] Publish Date: 13-Mar-2026 05:30 PM │ Bid Opening Date: 13-Apr-2026 03:00 PM Document Download/Sale Start Date: 13-Mar-2026 06:00 PM │ Document Download/Sale End Date: 10-Apr-2026 03:00 PM Clarification Start Date: 13-Mar-2026 06:00 PM │ Clarification End Date: 19-Mar-2026 03:00 PM Bid Submission Start Date: 25-Mar-2026 09:00 AM │ Bid Submission End Date: 10-Apr-2026 03:00 PM Pre Bid Meeting Date: 24-Mar-2026 03:00 PM [Critical Dates]
File Size Type Action
Timeextension.pdf 107.73 PDF
View document Sign-in required

Work details

Location, category, and schedule for this procurement.

Location Behala 132 KV Sub-station under Behala Area Office
Category Project Work
Period of work 120 days
Bid validity 90 days

Tender basics

Tender type Open Tender
Form of contract Item Wise
Tender category Works
No. of covers 2
Organisation chain WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED||TRANSMISSION OANDM HQ
Source portal wbtenders.gov.in

Authority details

Inviting authority Additional Chief Engineer KTZ
Address 3rd Floor, Administrative Building, Kasba 220 KV Sub-Station Premises 21, Chowbaga Road, P.O.and P.S.Tiljala, Kolkata -700039
Payment instruments Online , Online